2003, Trakya Cam (TCS) Mersin TR4 Turnkey Pattern Line Project
Elmak made the line design, mechanical equipments, electrical and control system of the new pattern line in Mersin.
Elmak did also the integration of the robotics.
The line specifications:
| Max ribbon speed |
: |
0,13 m/sn |
| Thickness |
: |
3-12 mm |
| Capacity |
: |
150 tons/day |
Components and machines supplied by Elmak:
|
· |
Conveyors |
· |
Selvedge conveyor |
· |
Washing machines |
| · |
Y-cutting |
· |
Digitizer |
· |
X-cutting |
| · |
Breakers |
· |
End breakers |
· |
Optimization |
| · |
PLC and MCC panels |
· |
Robotics integration |
· |
Remote monitoring |
 |
| |
Same sample Scada screens, line design, line photos |
|
2000, Trakya Cam (TCS) Luleburgaz TR2 Float Line Modernization Project
Elmak did the modernization of TR2 float line which was originally build by Pilkington in 1990 as a second line.
Redesign and replacement of all electrical and computer related systems is made by Elmak.
Elmak completely changed parts below while the cold maintenance
(2 robot and 1 stacker for J, 2 stacker for ME, 2 stacker for Split size).
The line specifications:
| Max ribbon speed |
: |
0,34 m/sn |
| Thickness |
: |
2-19 mm |
| Capacity |
: |
600 tons/day |
Components and Machines Modernized by Elmak
|
· |
Conveyors controls |
· |
Washing machines |
· |
Y-cutting |
| · |
Fault detection camera integration, (isra) |
· |
Digitizer |
· |
X-cutting |
| · |
Breakers |
· |
End breakers |
· |
Optimization |
| · |
PLC and MCC panels |
· |
Robotics integration |
· |
Remote monitoring |
 |
| |
Same sample Scada screens, line design, line photos |
|
1996 TCS-Luleburgaz TR1 Float Line End Horizontal Stacker Automation Project
The modernization of stacking machine which was build by Sodemeca in 1980 and its integration to the new line.
New PLC and computer visualization was designed and implemented.
|
|